PROBLEMS

13.132    Draw the PERT network associated with the following activities.
            
    
    Immediate Predecessor
A    -
B    A
C    A
D    B
E    B
F    C
G    D
H    E, F

 
ANSWER:


13.133    Given:
Activity    Optimistic    Most Likely    Pessimistic
A    3    4    5
B    6    7    14
C    2    3    10
D    0.5    1    1.5
E    6    9    12
F    4    5    12
G    1    3    11


    


    

    Determine:

        (a)    the critical path
        (b)    the probability that the project will be completed in 22 weeks

         ANSWER:
13.134    The following represent activities in a major construction project.  Draw the network to represent this situation.

Activity    Immediate Predecessor
A    -
B    -
C    A
D    B
E    B
F    C, D
G    E
H    F, G
    
    


13.135    A small software development project has five major activities.  The times are estimated and provided in the table below.  Find the expected time for completing this project.

Activity    Immediate
Predecessor    a    m    b
A        2    5    8
B        3    6    9
C    A    4    7    10
D    B    2    5    14
E    C    3    3    3


    (a)  What is the expected completion time for this project?
    (b)  What variance would be used in finding probabilities of finishing by a certain time?
 
    

13.136    A project has an expected completion time of 40 weeks and a standard deviation of 5 weeks.  It is assumed that the project completion time is normally distributed.

    (a) What is the probability of finishing the project in 50 weeks or less?
    (b) What is the probability of finishing the project in 38 weeks or less?
    (c) The due date for the project is set so that there is a 90 percent chance that the project will be finished by this date.  What is the due date?

    

13.137    Development of a new deluxe version of a particular software product is being considered.  The activities necessary for the completion of this are listed in the table below.

Activity    Normal Time    Crash Time    Normal Cost    Crash Cost    Immediate
Predecessor
A    4    3    2000    2600    -
B    2    1    2200    2800    -
C    3    3    500    500    -
D    8    4    2300    2600    A
E    6    3    900    1200    B
F    3    2    3000    4200    C
G    4    2    1400    2000    D,E

    (a)    What is the project completion date?
    (b)    What is the total cost required for completing this project on normal time?
    (c)    If you wish to reduce the time required to complete this project by one week, which activity should be crashed, and how much will this increase the total cost?
 

13.138    Draw the PERT network associated with the following activities.
    
    Immediate Predecessor
A    -
B    A
C    A
D    B
E    B
F    C, E
G    A, D
H    F
I    F
J    G, H, I


13.139    Given:

Activity    Optimistic    Most Likely    Pessimistic
A    3    4    5
B    6    7    14
C    2    3    10
D    6    9    12
E    4    5    12
F    1    3    11
G    1    2    9
H    2    5    8
I    1    4    7


    


    


Determine:

     (a)    the critical path
    (b)    the probability that the project will be completed in 22 weeks

          
13.140    The following table represents activities in a major construction project.  Draw the network to represent this situation.

Activity    Immediate Predecessor
A    -
B    -
C    B
D    B
E    A, C
F    D
G    E, F
H    B
I    G, H
    

13.141    A small software development project has four major activities.  The times are estimated and provided in the table below.  Find the expected time for completing this project.

Activity    Immediate
Predecessor    a    m    b
A        2    5    8
B        3    6    9
C    A    4    7    10
D    B    2    5    14
E    D    3    3    3
F    C    6    8    10
G    E, F    1    1    1
H    C    6    10    14
I    G, H    3    4    5


    (a)    What is the expected completion time for this project?
    (b)    What variance would be used in finding probabilities of finishing by a certain time?
 


13.142    A project has an expected completion time of 50 weeks and a standard deviation of 7 weeks.  It is assumed that the project completion time is normally distributed.

    (a)    What is the probability of finishing the project in 50 weeks or less?
    (b)    What is the probability of finishing the project in 55 weeks or more?
    (c)    What is the probability of finishing the project in 44 weeks or less?
    (d)    The due date for the project is set so that there is a 90 percent chance that the project will be finished by this date.  What is the due date?

    

13.143    Development of a new deluxe version of a particular software product is being considered.  The activities necessary for the completion of this are listed in the table below.

Activity    Normal Time    Crash Time    Normal Cost    Crash Cost    Immediate
Predecessor
                    
A    4    3    2,000    2,600    -
B    5    3    2,200    2,800    -
C    3    3    500    500    -
D    8    4    2,400    2,600    A
E    6    3    900    1,200    B
F    3    2    3,000    4,200    C
G    4    2    1,700    2,000    D,E

    (a)    If you wish to reduce the time required to complete this project by two weeks, which activity(ies) should be crashed, and how much will this increase the total cost?
    (b)  What would be the added cost if you wanted to complete the project in the minimum time possible?

    

SHORT ANSWER/ESSAY

13.144    PERT is the acronym for

13.145    CPM is the acronym for

    

13.146    In a PERT analysis, how is the optimistic time defined?

    

13.147    In a PERT analysis, how is the most likely time defined?

    

13.148    In PERT analysis, how is the pessimistic activity time defined?

    

13.149    In PERT/CPM, what is meant by the critical path?

    
 

Available Answer
$ 50.00

[Solved] ACC 501 Project Management CHAPTER 13 (PROBLEMS&ESSAY/ANSWER)

  • This solution is not purchased yet.
  • Submitted On 01 Jun, 2016 10:15:48
Answer posted by
Online Tutor Profile
solution
PROBLEMS 13.132 Draw the PERT network associated with the following activities. Immediate Predecessor A - B A C A D B E B F C G D H E, F ANSWER: 13.133 Given: Activity Optimistic Most Likely Pessimistic A 3 4 5 B 6 7 14 C 2 3 10 D 0.5 1 1.5 E 6 9 12 F 4 5 12 G 1 3 11 Determine: (a) the critical path (b) the probability that the project will be completed in 22 weeks ANSWER: 13.134 The following represent activities in a major construction project. Draw the network to represent this situation. Activity Immediate Predecessor A - B - C A D B E B F C, D G E H F, G 13.135 A small software development project has five major activities. The times are estimated and provided in the table below. Find the expected time for completing this project. Activity Immediate Predecessor a m b A  2 5 8 B  3 6 9 C A 4 7 10 D B 2 5 14 E C 3 3 3 (a) What is the expected completion time for this project? (b) What variance would be used in finding probabilities of finishing by a certain time? 13.136 A project has an expected completion time of 40 weeks and a standard deviation of 5 weeks. It is assumed that the project completion time is normally distributed. (a)...
Buy now to view the complete solution
Other Similar Questions
User Profile
Halsey

ACC 501 Project Management CHAPTER 13 (PROBLEMS&ESSAY/ANSWER)

PROBLEMS 13.132 Draw the PERT network associated with the following activities. Immediate Predecessor A - B A C A D B E B F C G D H E, F ANSWER: 13.133 Given: Activity Optimistic Most Likely Pessimistic A...
User Profile
Halsey

ACC 501 Project Management CHAPTER 13 (MULTIPLE CHOICE SOLUTION)

MULTIPLE CHOICE 13.47 The critical path of a network is the (a) shortest time path through the network. (b) path with the fewest activities. (c) path with the most activities. (d) longest time path through the network. ...
User Profile
Halsey

ACC 501 Project Management CHAPTER 13 (TRUE/FALSE SOLUTION)

TRUE/FALSE 13.1 PERT and CPM are quantitative analysis tools designed to schedule and control large projects. 13.2 PERT is a deterministic analysis tool allowing for precise times of activities within a project. 13.3 PER...
User Profile
Halsey

ACC 501 Project Management CHAPTER 13 COMPLETE SOLUTION (T/F; MULTIPLE CHOICE; PROBLEMS; ESSAY/ANSW)

TRUE/FALSE 13.1 PERT and CPM are quantitative analysis tools designed to schedule and control large projects. 13.2 PERT is a deterministic analysis tool allowing for precise times of activities within a project. 13.3 PER...

The benefits of buying study notes from CourseMerits

homeworkhelptime
Assurance Of Timely Delivery
We value your patience, and to ensure you always receive your homework help within the promised time, our dedicated team of tutors begins their work as soon as the request arrives.
tutoring
Best Price In The Market
All the services that are available on our page cost only a nominal amount of money. In fact, the prices are lower than the industry standards. You can always expect value for money from us.
tutorsupport
Uninterrupted 24/7 Support
Our customer support wing remains online 24x7 to provide you seamless assistance. Also, when you post a query or a request here, you can expect an immediate response from our side.
closebutton

$ 629.35