Cash-back offer from May 20th to 25th, 2024: Get a flat 10% cash-back credited to your account for a minimum transaction of $50.Post Your Questions Today!

Question DetailsNormal
$ 20.00

PROJ592 Proj Cost Schedule Control Week 6 Quizzes Versions

Question posted by
Online Tutor Profile
request

PROJ592 Proj Cost Schedule Control Week 6 Quizzes Versions

Available Answer
$ 20.00

[Solved] PROJ592 Proj Cost Schedule Control Week 6 Quizzes Versions

  • This solution is not purchased yet.
  • Submitted On 29 Sep, 2015 07:41:35
Answer posted by
Online Tutor Profile
solution
PROJ 592 Project Cost and Schedule Control PROJ 592 Week 6 (Version 1) 1. Question : (TCO B) Crashing Problem Using the network below and the additional information provided, find: (a) The crash cost per day per activity? (b) Which activities should be crashed to meet a project deadline of 12 days at minimum cost? (c) What is the extra cost to crash the project? Activity Normal Time Crash Time Normal Cost Crash Cost A 5 3 $300 $600 B 3 2 $250 $450 C 6 4 $400 $500 D 5 3 $150 $400 2. Question : (TCO F) We have discussed at length the Earned Value Management process. I am sure all of you have used the traditional process of assessing projects where we compare actual dollars spent to the amount we had planned to spend. This was quick and easy, but it has its shortcomings, and the Earned Value Management process is said to be better. (a) Why is this traditional approach different from using earned value when assessing project performance? (b) Describe the EVM process used to determine how far our project is ahead of or behind schedule. 3. Question : (TCO E) The following information is extracted from a project to develop a state of the art alternative power energy storage device: Activity Duration Predecessors Resources A 4 days -- 1 Research Engineer B 3 days A 1 Marketing Specialist C 5 days A 1 Design Engineer D 3 days A 1 Design Engineer E 3 days B 1 Prototype Builder F 2 days D 1 Test Engineer The Owner has stipulated that in order to provide continuity throughout the project, the same individual must handle all activities under his or her discipline. Activities on this project cannot be split. (a) Identify any resource conflicts in the above project. State the activities involved, the time frame of the conflict(s), which resources(s) are involved, and the quantity required. (b) Given the owner's stipulation regarding project continuity, and the need to minimize project duration, how can this conflict be resolved? What will be the effect on the project duration? 4. Question : (TCO F) The following data were obtained from an Information Systems project to upgrade and expand a Local Area Network: Activity Duration Predecessors Task Budget A 3 Days --- $4,920 B 6 Days --- $7,680 C 3 Days A $15,140 D 2 Days B $4,980 E 3 Days B $5,630 F 2 Days C, D $2,270 At the end of Day 7, the status of the project is as follows: Activity % Complete Actual Cost A 100% $4,200 B 100% $8,740 C ...
Buy now to view the complete solution
Other Similar Questions
User Profile
miche...

PROJ592 Proj Cost Schedule Week 7 Course Project Indoor Theme Park

Directions For CP2 you will set your CP1 project and document deliverable aside and start fresh. Your task is to use this document and the data provided to create a project file using Microsoft Project. The data below will es...
User Profile
miche...

PROJ592 Proj Cost Schedule Control Week 6 Quizzes Versions

PROJ 592 Project Cost and Schedule Control PROJ 592 Week 6 (Version 1) 1. Question : (TCO B) Crashing Problem Using the network below and the additional information provided, find: (a) The crash cost per day per activity? (b...
User Profile
miche...

PROJ592 Proj Cost Schedule Control Week 3 Quizzes Versions

PROJ 592 Project Cost and Schedule Control PROJ 592 Week 3 Quiz (Version 1) 1. Question : (TCO B) Three-point estimate: The SuperFlyer Corporation is developing a revolutionary flying disc. The new toy can fly straight over...

The benefits of buying study notes from CourseMerits

homeworkhelptime
Assurance Of Timely Delivery
We value your patience, and to ensure you always receive your homework help within the promised time, our dedicated team of tutors begins their work as soon as the request arrives.
tutoring
Best Price In The Market
All the services that are available on our page cost only a nominal amount of money. In fact, the prices are lower than the industry standards. You can always expect value for money from us.
tutorsupport
Uninterrupted 24/7 Support
Our customer support wing remains online 24x7 to provide you seamless assistance. Also, when you post a query or a request here, you can expect an immediate response from our side.
closebutton

$ 629.35