The Air Force needs to modify an aircraft to increase its range by 20%.
This improvement in performance will entail extensive developmental
testing as well as independent operational testing. The production line
for this aircraft shut down six months ago. What type of appropriation
should be used to pay for the development and testing of this product
improvement? [Identify the proper DoD Appropriation Category to be used for each of the
phases of a Product Improvement Program.]
Research, Development, Test and Evaluation
(RDT&E)
Procureme
nt
Operations and Maintenance
(O&M)
Expired
funds
2) ________duties are tailored at the request of the Program Manager (PM)
and are written in the Memorandum of Agreement, signed by both the PM
and the Contract Administration Office (CAO) Commander (Please note the
CAO Commander was previously referred to as the Contract Management
Office (CMO) Commander). [Identify the relationship between the Program Management
Office, the Procuring Contracting Officer, Administrative Contracting Officer, and Program
Integrator.]
Program
Integrator
Program Support
Team
Administrative Contracting
Officer
Procuring Contracting
Officer
3) When both parties agree to definitize a contract change before the work is
begun, the change is made contractually through a __________. [Contrast a
Change Order with a Supplemental Agreement.]

Available Answer
$ 20.00

[Solved] ACQ202 Module 5 Exam 2021

  • This solution is not purchased yet.
  • Submitted On 04 Oct, 2021 10:52:01
Answer posted by
Online Tutor Profile
solution
The Air Force needs to modify an aircraft to increase its range by 20%. This improvement in performance will entail extensive developmental testing as well as independent operational testing. The production line for this aircraft shut down six months ago. What type of appropriation should be used to pay for the development and testing of this ...
Buy now to view the complete solution
attachment
Attachment
Other Similar Questions
User Profile
Grade...

ACQ202 Module 4 Exam, Part II 2021

1) Which test would a contractor conduct on a software item before they integrate it with hardware? [Distinguish among various types of Developmental Test and Evaluation (DT&E) (e.g., Production Qualification Tests, Product...
User Profile
Grade...

ACQ202 Module 5 Exam 2021

The Air Force needs to modify an aircraft to increase its range by 20%. This improvement in performance will entail extensive developmental testing as well as independent operational testing. The production line for this a...

The benefits of buying study notes from CourseMerits

homeworkhelptime
Assurance Of Timely Delivery
We value your patience, and to ensure you always receive your homework help within the promised time, our dedicated team of tutors begins their work as soon as the request arrives.
tutoring
Best Price In The Market
All the services that are available on our page cost only a nominal amount of money. In fact, the prices are lower than the industry standards. You can always expect value for money from us.
tutorsupport
Uninterrupted 24/7 Support
Our customer support wing remains online 24x7 to provide you seamless assistance. Also, when you post a query or a request here, you can expect an immediate response from our side.
closebutton

$ 629.35