Question DetailsNormal
$ 25.00

Arizona Semiconductor is trying to determine the best place to build a manufacturing plant |Solution

Question posted by
Online Tutor Profile
request

3.Arizona Semiconductor is trying to determine the best place to build a manufacturing plant.  Arizona wants it to be centrally located between six of its assembly facilities. These assembly facilities are mapped on a two-dimensional grid using x,y coordinates as follows:

Facility

x

y

1

12

101

2

33

42

3

22

75

4

38

82

5

24

69

6

35

48

Where should the new manufacturing plant be built in order to minimize the distance between all the assembly facilities? The answer should be an x,y coordinate. Use the formula

 

to determine the distance between the new plant and an assembly facility, where x,y represents the location of the new plant and

 

represents the location of any particular assembly facility.

 

 

4. Arizona Semiconductor is trying to determine which R&D projects to fund for the upcoming fiscal year. The company has a limit of $200,000 and 10 researchers available for R&D to be spread between several projects. The table below shows the resources required for each project for the upcoming year and the expected annual profit from each project.

 

Project

1

2

3

4

5

6

Expense ($)

75

100

25

43

55

12

Number of Researchers

7

4

4

6

2

1

Profit ($)

92

85

4

72

50

15

 
  1. Which projects should the company choose to maximize expected annual profit? How much is that profit? Set this up as a spreadsheet using Solver.
  2. Suppose the company determines that that it must select either project 5 or 6 but not both. Does this change the list of projects the companies should undertake? How?
  3. If the company wants to increase the amount of R&D it does in the upcoming year, should it allocate more funding or hire more researchers? 

 

5. The AppleBerry Company makes a mix of three types of electronic devices: MP3 players, eReaders, and tablet computers. The company is trying to determine which products to make to optimize its profits. Each product requires a specific number of hours in fabrication, assembly, and machining. In addition, to save on expenses, all the devices have been engineered to use the same basic raw materials. The table below details the hours and costs involved, as well as the profit per device. AppleBerry has a total of 2000 hours of fabrication, 3200 hours of assembly, and 1600 hours of machining currently available per month. It also has budgeted to purchase $9200 of raw materials each month.

Device

Fabrication Hours Required

Assembly Hours Required

Machining Hours Required

$ of raw Materials Needed

Profit per Device

MP3 Player

6

6

9

$30

$16

eReader

6

8

6

$40

$20

Tablet

2

12

8

$25

$14

 
Answer the following questions:

  1. Given the current situation, what product mix should AppleBerry use to maximize its monthly profits? What is the optimized monthly profit? Set this up as a spreadsheet using Solver.
  2. If AppleBerry chooses to commit more resources to increase profits, should it purchase more fabrication time, assembly time, machining time, or raw materials?

 

 

6. Snoo Coffee Company creates three blends of coffee: budget, classic, and premium. The coffee blends are composed of four ingredients: A, B, C, and D. The table below shows the percentage of each component that are in each blend and the cost per pound for that ingredient. The blends have a wholesale price of $2.50, $3.00, and $4.50 for budget, classic, and premium, respectively.  A limited amount of each ingredient is available on a weekly basis.

Ingredient

Budget

Classic

Premium

Cost/lb.

Max Weekly Availability

A

25%

35%

0%

$0.60

40,000

B

55%

25%

0%

$0.80

20,000

C

5%

10%

50%

$0.95

35,000

D

15%

30%

50%

$0.70

45,000

Snoo can make 100,000 pounds of coffee per week, and it wants to make a minimum of 25,000 pounds of each blend.  (20 points)

  1. In order to maximize weekly profits, how many pounds of each ingredient should be purchased?
  2. What is the shadow price of ingredient C?
  3. How much should Snoo be willing to pay for an additional pound of ingredient C to raise total profit?

 

Available Answer
$ 25.00

[Solved] Arizona Semiconductor is trying to determine the best place to build a manufacturing plant |Solution

  • This Solution has been Purchased 1 time
  • Submitted On 05 May, 2015 09:51:00
Answer posted by
Online Tutor Profile
solution
Where should the new manufacturing plant be built in order to minimize the distance between all the assembly facilities...
Buy now to view the complete solution
Other Similar Questions
User Profile
hesig...

HESI FUNDAMENTALS QUESTIONS WITH ANSWERS >ARIZONA STATE UNIVERSITY

HESI FUNDAMENTALS QUESTIONS WITH ANSWERS >ARIZONA STATE UNIVERSITY...
User Profile
hesig...

SCM 300 - Exam 2 Study Guide Arizona State University

SCM 300 - Exam 2 Study Guide Arizona State University...
User Profile
hesig...

SCM 300- Final Exam Questions With Answers Satisfaction Guaranteed >Arizona State University

SCM 300- Final Exam Questions With Answers Satisfaction Guaranteed >Arizona State University...
User Profile
Acade...

Arizona State University School ASM 42288 Exam 3 complete solution

Arizona State University School ASM 42288 Exam 3 complete solution...
User Profile
maste...

Arizona State University EXW 73118 Quiz 2

Arizona State University EXW 73118 Quiz 2 Arizona State University EXW 73118 Quiz 2 Arizona State University EXW 73118 Quiz 2 Arizona State University EXW 73118 Quiz 2 Arizona State University EXW 73118 Quiz 2...

The benefits of buying study notes from CourseMerits

homeworkhelptime
Assurance Of Timely Delivery
We value your patience, and to ensure you always receive your homework help within the promised time, our dedicated team of tutors begins their work as soon as the request arrives.
tutoring
Best Price In The Market
All the services that are available on our page cost only a nominal amount of money. In fact, the prices are lower than the industry standards. You can always expect value for money from us.
tutorsupport
Uninterrupted 24/7 Support
Our customer support wing remains online 24x7 to provide you seamless assistance. Also, when you post a query or a request here, you can expect an immediate response from our side.
closebutton

$ 629.35